Construction of bay No. 18 in 220 kV Switchyard at Maritsa East 2 TPP

Assignor
NEC EAD High Voltage Network Enterprise

Location:
Kovachevo Village, Radnevo Municipality

Assigned: 1999 / Completed: 1999

Activities

  • Installation of Primary Equipment: circuit breakers, current measuring transformers, voltage measuring transformers, disconnectors, pipe system;
  • Installation of three-phase distribution busbar system and branch connection links;
  • Laying, tests and connection of control cables.

 

 