Complete engineering of Lighting and Socket Installation in Gypsum Dewatering Plant at the FGD Plant in Maritsa East 2 TPP

Assignor:
АВВ Utility Automation GmbH. Germany; Main Contractor: Consortium INA/SHU

Location:
Kovachevo Village, Radnevo Municipality

Assigned: 2002 / Completed: 2003

Project description

After completion of the Project for installation and commissioning of main facilities in the Flue Gas Desulfurization Plant (FGD) and the Gypsum-Dewatering Plant (GDP) in Maritza East 2 TPP, at the end of 2002 ABB Utility Automation GmbH. Germany assigned to EL KONTROL a new order for complete engineering of a Lighting system, installation of 6 kV switchgear and 0,4 kV switchgear in the GDP at the FGD in Maritza East 2 TPP.

Activities

  • Engineering and electrical installation of Lighting and socket System;
  • Installation of cable racks and grids for laying of power and control cables;
  • Laying and connection of 0.4 kV and 6 kV power cables, installation of cable terminals;
  • Installation of 6kV switchgear and 0,4kV switchgear;
  • Laying and connection of control cables;
  • Control tests of cables and motors, issue of Inspection Certificates.

 

 

 