Assignor:
АВВ Utility Automation GmbH. Germany; Main Contractor: Consortium INA/SHU
Location:
Kovachevo Village, Radnevo Municipality
Assigned: 2002 / Completed: 2003
Project description
After completion of the Project for installation and commissioning of main facilities in the Flue Gas Desulfurization Plant (FGD) and the Gypsum-Dewatering Plant (GDP) in Maritza East 2 TPP, at the end of 2002 ABB Utility Automation GmbH. Germany assigned to EL KONTROL a new order for complete engineering of a Lighting system, installation of 6 kV switchgear and 0,4 kV switchgear in the GDP at the FGD in Maritza East 2 TPP.
Activities
- Engineering and electrical installation of Lighting and socket System;
- Installation of cable racks and grids for laying of power and control cables;
- Laying and connection of 0.4 kV and 6 kV power cables, installation of cable terminals;
- Installation of 6kV switchgear and 0,4kV switchgear;
- Laying and connection of control cables;
- Control tests of cables and motors, issue of Inspection Certificates.