Complete engineering for substitution of electrical equipment in 0,4 kV Indoor Switchgears, in Unit 1, Unit 2, Unit 3 and Unit 4 of Maritsa East 2 TPP

Assignor:
Siemens EOOD - Bulgaria

Location:
Kovachevo Village, Radnevo Municipality

Assigned: 2006 / Completed: 2008

Activities

  • Dismantle of 0,4 kV electrical equipment from all indoor switchgears in Units 1, 2, 3 and 4 of Maritsa East 2 TPP;
  • Installation of new 0,4 kV electrical equipment produced by SIEMENS A.G. Germany;
  • Installation and electrical tests of 6,3/ 0,4 kV power transformers;
  • Electrical tests and set-up of relay protection for 0,4 kV equipment;
  • Commissioning of 0,4 kV indoor switchgears.

 

 