Assignor:
Electricity System Operator EAD
Location:
Parvomay
Assigned: 2009 / Completed: 2009
Project description
Substitution of relay protection, control switchboards, relay panels and marshalling panels in the 2-nd section of the 110kV Switchyard.
Activities
Primary Commutation:
- Substitution of relay protection, control switchboards, relay panels and marshalling panels in the 2-nd section of the 110kV Switchyard.
Secondary Commutation:
- Manufacturing and installation of relay panels and control panels;
- Set-up of relay protection;
- Control tests of the installed equipment;
- Laying and connection of control cables.