Assignor:
Enel Maritsa East 3 AD
Location:
Mednikarovo Village, Galabovo Municipality
Assigned: 2008 / Completed: 2009
Project description
In December 2007, after a successful tender for a public procurement, EL KONTROL signed a contract for Rehabilitation of The Coal Handling Plant in Enel Maritsa East 3 TPP. Order includes completion of electrical and C&I works.
Activities
- Substitution of 6,3 kV switchgear, supply and installation of electrical equipment;
- Substitution of 0,4 kV switchgear;
- Substitution of MV transformers;
- Construction of grounding system and connection of the installed equipment thereto;
- Laying and connection of 6,3 kV and 0,4 kV cables;
- Rehabilitation of existing cable trays and construction of new ones;
- Construction of security system for belt conveyors with emergency ropes;
- Supply, erection and wiring of speed controller and deviation controller of belt conveyor and ultrasonic sensors for product level control.