Design, installation and commissioning of C&I and electrical equipment in Coal Handling Plant, Enel Maritsa East 3 TPP

Assignor:
Enel Maritsa East 3 AD

Location:
Mednikarovo Village, Galabovo Municipality

Assigned: 2008 / Completed: 2009

Project description

In December 2007, after a successful tender for a public procurement, EL KONTROL signed a contract for Rehabilitation of The Coal Handling Plant in Enel Maritsa East 3 TPP. Order includes completion of electrical and C&I works.

Activities

  • Substitution of 6,3 kV switchgear, supply and installation of electrical equipment;
  • Substitution of 0,4 kV switchgear;
  • Substitution of MV transformers;
  • Construction of grounding system and connection of the installed equipment thereto;
  • Laying and connection of 6,3 kV and 0,4 kV cables;
  • Rehabilitation of existing cable trays and construction of new ones;
  • Construction of security system for belt conveyors with emergency ropes;
  • Supply, erection and wiring of speed controller and deviation controller of belt conveyor and ultrasonic sensors for product level control.

 

 