In January 2012 EL KONTROL commenced an order for the electrical part of the Project for construction of Photovoltaic Park Letnitsa. Order was contracted with Schneider Electric France and concerns erection of a new PV Power Plant near Letnitsa town in Lovech District.
Activities
- Delivery, installation and connection of MV and LV power cables;
- Delivery, installation and connection of fiber-optic and communication cables;
- Delivery and erection of earthing installation for PV panels;
- Delivery and installation of MV cable terminals;
- Installation of LV switchboards;
- Connection of PV panels and commissioning of the PV Park.