Project description
The Order for repair of concrete foundations for equipment in 110 kV Switchyard of 400 kV Substation Burgas is part of a major project for rehabilitation of the Substation.
Activities
- Construction of concrete tables and foundations for the equipment in 110 kV Switchyard;
- Construction of tubular grid of steel conduits