Elaboration and realization of a Design for substitution of circuit breakers and disconnectors in 20 kV Indoor Switchgear at Oil-tank farm, located in LUKOIL Neftohim Burgas AD

Assignor:
LUKOIL Neftohim Burgas AD

Location:
Burgas

Assigned: 2013 / Completed: 2013

Project description

Scope of the Contract includes elaboration of detailed design (Primary and Secondary commutation) for reconstruction of an existing 20 kV Indoor SWG into 20 kV air-insulated metal-clad SWG, located in 110/20/6 kV Substation No. 2, situated in Oil-tank farm Rosenets on the territory of LUKOIL Neftohim Burgas AD. Contract also includes further realization of the Design, and commissioning of the equipment installed.

Activities

  • Elaboration of detailed design for reconstruction of an existing 20 kV Indoor SWG at 110/20/6 kV Substation No. 2. Design includes Electrical part,
  • Construction part, and Architectural part.
  • Dismantle of equipment from 20 kV Indoor SWG: circuit breakers, disconnectors, measuring transformers, metal structure, and busbar system with adjacent support insulators
  • Reconstruction works: plastering, painting, floor repair
  • Installation Lighting system
  • Delivery and installation of 20 kV air-insulated metal-clad SWG
  • Delivery, laying and connection of power cables and control cables
  • Reconstruction of trade metering panel; reconstruction of signalization panel; assembly and installation of control metering panel
  • Commissioning works and putting of all the equipment installed under operational use.

 

 