Changing the power supply scheme of 6/0.4 kV Substation No. 214, to direct power supply from 6 kV Indoor Switchgear of S/st GPP-2, first and second section

Assignor:
LUKOIL Neftohim Burgas AD

Location:
Burgas

Assigned: 2014 / Completed: 2014

Project description

Substation No. 214 is located in LUKOIL Neftohim Burgas AD oil refinery.

The Project concerns provision of direct power supply for S/st 214 from 6 kV Indoor Switchgear of S/st GPP-2, distribution of the load between S/st No. 214 and S/st 215, set-up of relay protection and microprocessor protection, installation of new electrometers for the incoming feeders of S/st 214.

Activities

  • Dismantle of existing power cables;
  • Dismantle of cable racks;
  • Supply, laying and connection of power cables;
  • Delivery and installation of electrometers;
  • Painting and applying corrosion protection onto steel structures;
  • Set-up of relay protection;
  • Control tests and commissioning of S/st 214.

 

 