Reconstruction and modernization of 110/15.75/6.3 kV Main Step-down Substation-2 (GPP-2), located in LUKOIL Neftohim Burgas AD

Assignor:
LUKOIL Neftohim Burgas AD

Location:
Burgas

Assigned: 2013 / Completed: 2013

Project description

Project includes reconstruction of two bays in 110 kV Indoor Switchgear, and two outgoing feeders in 6 kV Indoor Switchgear of S/st GPP-2. Purpose of the reconstruction is to ensure power supply of a Heavy Residue Complex under construction on the territory of LUKOIL Neftohim Burgas AD.

Activities

Reconstruction of two bays in 110 kV Indoor Switchgear

  • Dismantle of existing equipment in 110 kV Indoor SWG;
  • Installation of equipment for bays in 110 kV Indoor SWG: 110 kV SF6 circuit breaker, 110 kV feeder disconnector, 110 kV current measuring transformers, and bushings;
  • Delivery and mounting of steel structures;
  • Secondary commutation in 110 kV Indoor SWG: dismantle and refurbishment of control panels, relay panels, and electric meter panels;
  • Assembly, installation and connection of control switchboards at 110 kV terminal bay;
  • Delivery, installation and connection of control cables;
  • Commissioning works;
  • Parameterizing and testing of relay protection.

Reconstruction of two feeder bays in 6 kV Indoor Switchgear

  • Dismantle of existing bays in 6 kV Indoor SWG;
  • Delivery and installation of support insulators and ring-core current transformers for earth protection;
  • Dismantle of existing current limiting reactors, installation of new ones and busbar installation;
  • Delivery and installation of 6 kV busbar, type examination passed;
  • Secondary commutation in 6 kV Indoor SWG: equipping of 6 kV SWG;
  • Delivery, laying and connection of control cables;
  • Commissioning works;
  • Parameterizing and testing of relay protection.

 

 