Assignor:
Biomass Distribution EOOD
Location:
Stroevo Village, Maritsa Municipality, Plovdiv District
Assigned: 2014 / Completed: 2016
Project description
Concrete transformer station (CTS) ‘Pellets’ is constructed to ensure work of Pelletization plant at the newly built Power Plant KARLOVO BIOMASS. The CTS is a prefabricated reinforced concrete building with 33 m2 built-up area, with technical data: 2 х 1000 kVA 20/0,4 kV.
Activities
Delivery and installation of the following:
- Monolithic concrete structure bottom foundation part
- A Switchgear (SWG) SIEMENS 8DJH 24 kV, 630 A
- Two Switchgears (SWG) SIEMENS 8DJH 24 kV, 200 A
- Two signalization panels
- UPS 1000 VA;
- MV cables, LV cables, cable ends
- Power oil-filled transformer 1000 kVA
Construction works:
- Excavation and reinforced concrete base
- Construction of earthing system
Commissioning works.