Substitution of control cables for 110/6 kV power transformers and repair of cubicles of 6 kV Indoor Switchgear, at Main Step-down Substation GPP-2

Assignor:
LUKOIL Neftochim Burgas AD

Location:
Burgas

Assigned: 2018 / Completed: 2018

Project description

Construction works take place at Main Step-down Substation GPP-2 in LUKOIL Neftochim Burgas AD Refinery.

Activities

Scope of works:

  • Dismantle of concrete covers of cable ditches
  • Dismantle of cables;
  • Installation and fixation of control cables onto steel structure; connection of power and control cables to power transformers;
  • Substitution of end switches, electromagnetic locks, and disconnector signaling devices in 6 kV cubicles;
  • Repair of 6 kV disconnectors;
  • Substitution of mesh fences for 6 kV cubicles’ doors with thick metal sheets;
  • Construction and repair works;
  • Commissioning works.

 

 