Complete engineering for substitution of electrical equipment in 0,4 kV Indoor Switchgears, in Unit 1, Unit 2, Unit 3 and Unit 4 of Maritsa East 2 TPP

Read more ...

Assignor:
Siemens EOOD - Bulgaria

Location:
Kovachevo Village, Radnevo Municipality

Assigned: 2006 / Completed: 2008

Delivery of electrical equipment and execution of electrical works for erection of Karlovo Biomass Power Plant at Stroevo Village

Read more ...

Assignor:
Equtec Bulgaria EOOD, a Branch of Equtec Iberia, Spain

Location:
Stroevo Village, Maritsa Municipality, Plovdiv District

Assigned: 2014 / Completed: 2017

Supervisory Control and Data Acquisition (SCADA) System of eight railway stations, three Main Section Posts (MSP), and two Traction Substations (TS) TS Voluyak and TS Aldomirovtsi, situated along the railway lot Sofia – Kalotina-West

Read more ...

Assignor:
Energoremont Holding AD

Location:
Sofia

Assigned: 2013/ Completed: 2014