Reconstruction of feeder bays for Substation 214 from Substation GPP-2, including installation of differential protection with Intertrip function for power supply cables

Read more ...

Assignor:
LUKOIL Neftochim Burgas AD

Location:
Burgas

Assigned: 2017 / Completed: 2017

Substitution of control cables for 110/6 kV power transformers and repair of cubicles of 6 kV Indoor Switchgear, at Main Step-down Substation GPP-2

Read more ...

Assignor:
LUKOIL Neftochim Burgas AD

Location:
Burgas

Assigned: 2018 / Completed: 2018